GUJARAT TECHNOLOGICAL UNIVERSITY
MBA ? SEMESTER 02? ? EXAMINATION ? SUMMER 2016
Subject Code: 2820006 Date: 27/05/2016
Subject Name: Production and OperationS Management (POM)
Time: 10.30 am to 01.30 pm Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q 1 (a) Answer the following questions by selecting the right options (06)
1. Four common types of control charts include all the following except:
a. X bar chart
b. T chart
c. P chart
d. C chart
2. Which of the following is not an event or concept associated with the quality revolution?
a. TQM (total quality management)
b. PERT/CPM
c. Business process reengineering
d. JIT
3. A ________layout encourages customer familiarity, has low costs, and is easy to clean.
a. free flow layout
b. grid layout
c. spine layout
d. loop layout
4. ___________ demand items are used in the process of producing a final product.
a. Dependent
b. Independent
c. Seasonal
d. Cyclical
5. Which of the following is not used to calculate probabilistic time estimates?
a. optimistic
b. most likely
c. least likely
d. pessimistic
6. The process of breaking an aggregate plan into more detailed plans is referred to as
a. collaborative planning
b. hierarchical planning
c. disaggregation
d. rough-cut planning
FirstRanker.com - FirstRanker's Choice
Page 1 of 5
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
MBA ? SEMESTER 02? ? EXAMINATION ? SUMMER 2016
Subject Code: 2820006 Date: 27/05/2016
Subject Name: Production and OperationS Management (POM)
Time: 10.30 am to 01.30 pm Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q 1 (a) Answer the following questions by selecting the right options (06)
1. Four common types of control charts include all the following except:
a. X bar chart
b. T chart
c. P chart
d. C chart
2. Which of the following is not an event or concept associated with the quality revolution?
a. TQM (total quality management)
b. PERT/CPM
c. Business process reengineering
d. JIT
3. A ________layout encourages customer familiarity, has low costs, and is easy to clean.
a. free flow layout
b. grid layout
c. spine layout
d. loop layout
4. ___________ demand items are used in the process of producing a final product.
a. Dependent
b. Independent
c. Seasonal
d. Cyclical
5. Which of the following is not used to calculate probabilistic time estimates?
a. optimistic
b. most likely
c. least likely
d. pessimistic
6. The process of breaking an aggregate plan into more detailed plans is referred to as
a. collaborative planning
b. hierarchical planning
c. disaggregation
d. rough-cut planning
Page 2 of 5
Q 1 (b) Give the definition of the following terms (04)
1. Demonstrated Capacity
2. Total Quality Management (TQM)
3. Periodic Inventory System
4. Business Process Reengineering (BPR)
Q 1 (c) Explain the term PERT & CPM with context to Project Management. Give the example
of projects where they would be applicable. (04)
Q 2 (a) Discuss the strategies to adjust capacity and manage demand along with examples. (07)
Q 2 (b) What is EOQ? Explain how order quantity is determined using the basic Economic Order
Quantity Model. (07)
OR
Q 2 (b) As a project manager of a large petrochemical refinery, how will you select the
appropriate location of a plant? Discuss various factors affecting your decision. (07)
Q 3 (a) What do you mean by Six Sigma? Explain the various analytical tools associated with
Six Sigma. (07)
Q 3 (b) The Basic Block Company needs to produce 4000 boxes of blocks per 40 hour week to
meet the upcoming holiday demand. The process of making blocks can be broken down
into six work elements. The precedence and time requirements for each element are as
follows. Draw and label a precedence diagram for the production process. Set up a
balanced assembly line and calculate the efficiency of the line. (07)
Work Element Precedence Performance Time (Min)
A - 0.10
B A 0.40
C A 0.50
D - 0.20
E C,D 0.60
F B,E 0.40
OR
Q 3 (a) Explain the different types of layout. Additionally differentiate between product and
process layout. (07)
Q 3 (b) I-75 Discount Carpet manufactures Cascade Carpet, which it sells in its adjoining
showroom store near the interstate. Estimated annual demand is 20000 yards of carpet
with an annual carrying cost of $2.75 per yard. The manufacturing facility operates the
same 360 days the store is open and produces 400 yards of carpet per day. The cost of
setting up the manufacturing process for the production run is $720. Determine the
optimal order size, total inventory cost, length of the time to receive an order, and
maximum inventory level. (07)
Q 4 (a) Discuss material handling principles and classify material handling equipments. (07)
Q 4 (b) The following table provides the information necessary to construct a project network
and project crash data
FirstRanker.com - FirstRanker's Choice
Page 1 of 5
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
MBA ? SEMESTER 02? ? EXAMINATION ? SUMMER 2016
Subject Code: 2820006 Date: 27/05/2016
Subject Name: Production and OperationS Management (POM)
Time: 10.30 am to 01.30 pm Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q 1 (a) Answer the following questions by selecting the right options (06)
1. Four common types of control charts include all the following except:
a. X bar chart
b. T chart
c. P chart
d. C chart
2. Which of the following is not an event or concept associated with the quality revolution?
a. TQM (total quality management)
b. PERT/CPM
c. Business process reengineering
d. JIT
3. A ________layout encourages customer familiarity, has low costs, and is easy to clean.
a. free flow layout
b. grid layout
c. spine layout
d. loop layout
4. ___________ demand items are used in the process of producing a final product.
a. Dependent
b. Independent
c. Seasonal
d. Cyclical
5. Which of the following is not used to calculate probabilistic time estimates?
a. optimistic
b. most likely
c. least likely
d. pessimistic
6. The process of breaking an aggregate plan into more detailed plans is referred to as
a. collaborative planning
b. hierarchical planning
c. disaggregation
d. rough-cut planning
Page 2 of 5
Q 1 (b) Give the definition of the following terms (04)
1. Demonstrated Capacity
2. Total Quality Management (TQM)
3. Periodic Inventory System
4. Business Process Reengineering (BPR)
Q 1 (c) Explain the term PERT & CPM with context to Project Management. Give the example
of projects where they would be applicable. (04)
Q 2 (a) Discuss the strategies to adjust capacity and manage demand along with examples. (07)
Q 2 (b) What is EOQ? Explain how order quantity is determined using the basic Economic Order
Quantity Model. (07)
OR
Q 2 (b) As a project manager of a large petrochemical refinery, how will you select the
appropriate location of a plant? Discuss various factors affecting your decision. (07)
Q 3 (a) What do you mean by Six Sigma? Explain the various analytical tools associated with
Six Sigma. (07)
Q 3 (b) The Basic Block Company needs to produce 4000 boxes of blocks per 40 hour week to
meet the upcoming holiday demand. The process of making blocks can be broken down
into six work elements. The precedence and time requirements for each element are as
follows. Draw and label a precedence diagram for the production process. Set up a
balanced assembly line and calculate the efficiency of the line. (07)
Work Element Precedence Performance Time (Min)
A - 0.10
B A 0.40
C A 0.50
D - 0.20
E C,D 0.60
F B,E 0.40
OR
Q 3 (a) Explain the different types of layout. Additionally differentiate between product and
process layout. (07)
Q 3 (b) I-75 Discount Carpet manufactures Cascade Carpet, which it sells in its adjoining
showroom store near the interstate. Estimated annual demand is 20000 yards of carpet
with an annual carrying cost of $2.75 per yard. The manufacturing facility operates the
same 360 days the store is open and produces 400 yards of carpet per day. The cost of
setting up the manufacturing process for the production run is $720. Determine the
optimal order size, total inventory cost, length of the time to receive an order, and
maximum inventory level. (07)
Q 4 (a) Discuss material handling principles and classify material handling equipments. (07)
Q 4 (b) The following table provides the information necessary to construct a project network
and project crash data
Page 3 of 5
Activity Predecessor Activity Time (Weeks) Activity Cost ($)
Normal Crash Normal Crash
A - 16 8 2000 4000
B - 14 9 1000 1800
C A 8 6 500 700
D A 5 4 600 1300
E B 4 2 1500 3000
F B 6 4 800 1600
G C 10 7 3000 4500
H D,E 15 10 5000 8000
Construct the project network, and crash the network so G and H complete at the same
time of 22 weeks. Also calculate the total crash cost. (07)
OR
Q 4 (a) What is Statistical Process Control (SPC) in Quality Management? Explain the difference
between attribute control charts and variable control charts. Elaborate with examples how
SPC is applied in case of services. (07)
Q 4 (b) Differentiate between production and operation. Additionally explain in detail the
objectives and functions of production planning and control. (07)
Q 5 The Shanghai Textile Mill was inspected and found to be in violation of a number of safety
regulations. The inspectors ordered the mill to alter some existing machinery to make it safe
and relocate some machinery to make safer passages and unobstructed entrances and exits.
The inspector gave the mill only 35 weeks to make the changes; if the changes were not
made by then, the mill would be fined $300000. The mill determined the activities in PERT
network that would have to be completed and then estimated the indicated activity times, as
shown in the table below:
Activity Description Predecessor
Time (Weeks)
a m b
A Order new machine - 1 2 4
B Plan new layout - 2 5 8
C Deter safety changes - 1 3 7
D Receive equipments A 5 10 23
E Hire new employees A 3 7 12
F Make plant alterations B 10 15 18
G Make change in existing machine C 7 9 11
H Train new employees D,E 2 4 7
I Install new equipments D,E,F 2 4 6
J Relocate old machine D,E,F,G 4 7 10
K Conduct employee safety H,I,J 2 3 4
Construct the PERT network and find the following
a. Expected Activity Time
b. Earliest / Latest Times / Slack
c. Critical Path
d. Expected project duration and variance
e. The probability that mill would be fined $300000 (14)
OR
FirstRanker.com - FirstRanker's Choice
Page 1 of 5
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
MBA ? SEMESTER 02? ? EXAMINATION ? SUMMER 2016
Subject Code: 2820006 Date: 27/05/2016
Subject Name: Production and OperationS Management (POM)
Time: 10.30 am to 01.30 pm Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q 1 (a) Answer the following questions by selecting the right options (06)
1. Four common types of control charts include all the following except:
a. X bar chart
b. T chart
c. P chart
d. C chart
2. Which of the following is not an event or concept associated with the quality revolution?
a. TQM (total quality management)
b. PERT/CPM
c. Business process reengineering
d. JIT
3. A ________layout encourages customer familiarity, has low costs, and is easy to clean.
a. free flow layout
b. grid layout
c. spine layout
d. loop layout
4. ___________ demand items are used in the process of producing a final product.
a. Dependent
b. Independent
c. Seasonal
d. Cyclical
5. Which of the following is not used to calculate probabilistic time estimates?
a. optimistic
b. most likely
c. least likely
d. pessimistic
6. The process of breaking an aggregate plan into more detailed plans is referred to as
a. collaborative planning
b. hierarchical planning
c. disaggregation
d. rough-cut planning
Page 2 of 5
Q 1 (b) Give the definition of the following terms (04)
1. Demonstrated Capacity
2. Total Quality Management (TQM)
3. Periodic Inventory System
4. Business Process Reengineering (BPR)
Q 1 (c) Explain the term PERT & CPM with context to Project Management. Give the example
of projects where they would be applicable. (04)
Q 2 (a) Discuss the strategies to adjust capacity and manage demand along with examples. (07)
Q 2 (b) What is EOQ? Explain how order quantity is determined using the basic Economic Order
Quantity Model. (07)
OR
Q 2 (b) As a project manager of a large petrochemical refinery, how will you select the
appropriate location of a plant? Discuss various factors affecting your decision. (07)
Q 3 (a) What do you mean by Six Sigma? Explain the various analytical tools associated with
Six Sigma. (07)
Q 3 (b) The Basic Block Company needs to produce 4000 boxes of blocks per 40 hour week to
meet the upcoming holiday demand. The process of making blocks can be broken down
into six work elements. The precedence and time requirements for each element are as
follows. Draw and label a precedence diagram for the production process. Set up a
balanced assembly line and calculate the efficiency of the line. (07)
Work Element Precedence Performance Time (Min)
A - 0.10
B A 0.40
C A 0.50
D - 0.20
E C,D 0.60
F B,E 0.40
OR
Q 3 (a) Explain the different types of layout. Additionally differentiate between product and
process layout. (07)
Q 3 (b) I-75 Discount Carpet manufactures Cascade Carpet, which it sells in its adjoining
showroom store near the interstate. Estimated annual demand is 20000 yards of carpet
with an annual carrying cost of $2.75 per yard. The manufacturing facility operates the
same 360 days the store is open and produces 400 yards of carpet per day. The cost of
setting up the manufacturing process for the production run is $720. Determine the
optimal order size, total inventory cost, length of the time to receive an order, and
maximum inventory level. (07)
Q 4 (a) Discuss material handling principles and classify material handling equipments. (07)
Q 4 (b) The following table provides the information necessary to construct a project network
and project crash data
Page 3 of 5
Activity Predecessor Activity Time (Weeks) Activity Cost ($)
Normal Crash Normal Crash
A - 16 8 2000 4000
B - 14 9 1000 1800
C A 8 6 500 700
D A 5 4 600 1300
E B 4 2 1500 3000
F B 6 4 800 1600
G C 10 7 3000 4500
H D,E 15 10 5000 8000
Construct the project network, and crash the network so G and H complete at the same
time of 22 weeks. Also calculate the total crash cost. (07)
OR
Q 4 (a) What is Statistical Process Control (SPC) in Quality Management? Explain the difference
between attribute control charts and variable control charts. Elaborate with examples how
SPC is applied in case of services. (07)
Q 4 (b) Differentiate between production and operation. Additionally explain in detail the
objectives and functions of production planning and control. (07)
Q 5 The Shanghai Textile Mill was inspected and found to be in violation of a number of safety
regulations. The inspectors ordered the mill to alter some existing machinery to make it safe
and relocate some machinery to make safer passages and unobstructed entrances and exits.
The inspector gave the mill only 35 weeks to make the changes; if the changes were not
made by then, the mill would be fined $300000. The mill determined the activities in PERT
network that would have to be completed and then estimated the indicated activity times, as
shown in the table below:
Activity Description Predecessor
Time (Weeks)
a m b
A Order new machine - 1 2 4
B Plan new layout - 2 5 8
C Deter safety changes - 1 3 7
D Receive equipments A 5 10 23
E Hire new employees A 3 7 12
F Make plant alterations B 10 15 18
G Make change in existing machine C 7 9 11
H Train new employees D,E 2 4 7
I Install new equipments D,E,F 2 4 6
J Relocate old machine D,E,F,G 4 7 10
K Conduct employee safety H,I,J 2 3 4
Construct the PERT network and find the following
a. Expected Activity Time
b. Earliest / Latest Times / Slack
c. Critical Path
d. Expected project duration and variance
e. The probability that mill would be fined $300000 (14)
OR
Page 4 of 5
Q 5 Read the following case and answer the question below (14)
Steve Jobs and Apple
Late Steve Jobs completed the education only till high school when he dropped out from Reed
College, Oregon. Another drop out from University of California at Berkley was Stephen
Wozniak, who started working for Hewlett-Packard (HP) and came in contact with a summer
intern there ? Jobs. Wozniak was an engineering wizard, who was influenced by Jobs to quit his
job at HP and start a new venture. Thus Apple Computer Corporation was founded by Jobs
alongwith Wozniak in 1976 in his car garbage. At that time, nobody had imagined that large
computers hitherto confined to scientific installations could be configured for personal use by
individuals. The Apple computer designed and created by the duo received orders of 25 units
from the local electronics retailer and from thereon, the story of first personal computer was
started. Rest is now history.
Apple?s approach to designing new products is rather unconventional, as if symbolizing the
exotic leadership style of Jobs. If Steve?s words, ?Simplicity is the ultimate sophistication.? A
typical example is the IPod, which was designed to play the music through a miniature device
and do nothing else. The platform strategy is clearly evident in use of OSX operating system in
Macintosh, PCs, iPhone, and iPad. In fact, iPad is a natural extension of the iPhone in terms of
touch screen and other common user interfaces/applications. This promotes reusability of parts,
components, software etc., while ensuring less training on part of existing customers using Apple
Products. Future applicability of current products through cross-pollination of internal ideas and
technologies is an important aspect of Apple designs. Another facet of its approach is
?participatory design? whereby customers play an active role in design process. In the
development stages, the experiences and problems faced by a sample set of customers using a
software/product are meticulously observed. The focus then shifts to finding simple yet effective
solutions to such problems for improvising the designs. The customer involvement is ?iterative?
in nature, that is, there experiences are continually monitored to identify the scope of further
improvement. This explains the progressive release of latest versions of products, taking for
example iPhone 4 has innovative features such as video calling with Face time, retina display
with 960 by 640 resolution, HD video recording, 5 megapixel camera with LED flash, dual-mic
noise suppression, and much more. What sets Apple products apart from competition is their
aesthetic appeal. The pristine white colour almost becomes synonymous with Apple products
with ?snow white skin?, when the company introduced vibrant colours in some of its products
like iPods. This simply shows the flexibility and dynamism in Apple designs rather than getting
trapped in statics of currently successful designs. The future outlook and boldness is clearly
hallmark of Apple designs, which always leaves the competition to do lots of catching up.
Experts argue that Apple products are not radical innovations but improvisations of existing
products in the market. According to them, neither was iPod the first MP3 player nor was iPhone
the first smartphone with a touch screen. iPad was not the first tablet either. The bottom line is
that Apple not only learns from its own mistakes, but also from the competitor?s mistakes.
Apple?s mission is not to be the first but clearly to be the best.
Job?s idea of innovation in design is aptly captured by his statement below:
FirstRanker.com - FirstRanker's Choice
Page 1 of 5
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
MBA ? SEMESTER 02? ? EXAMINATION ? SUMMER 2016
Subject Code: 2820006 Date: 27/05/2016
Subject Name: Production and OperationS Management (POM)
Time: 10.30 am to 01.30 pm Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q 1 (a) Answer the following questions by selecting the right options (06)
1. Four common types of control charts include all the following except:
a. X bar chart
b. T chart
c. P chart
d. C chart
2. Which of the following is not an event or concept associated with the quality revolution?
a. TQM (total quality management)
b. PERT/CPM
c. Business process reengineering
d. JIT
3. A ________layout encourages customer familiarity, has low costs, and is easy to clean.
a. free flow layout
b. grid layout
c. spine layout
d. loop layout
4. ___________ demand items are used in the process of producing a final product.
a. Dependent
b. Independent
c. Seasonal
d. Cyclical
5. Which of the following is not used to calculate probabilistic time estimates?
a. optimistic
b. most likely
c. least likely
d. pessimistic
6. The process of breaking an aggregate plan into more detailed plans is referred to as
a. collaborative planning
b. hierarchical planning
c. disaggregation
d. rough-cut planning
Page 2 of 5
Q 1 (b) Give the definition of the following terms (04)
1. Demonstrated Capacity
2. Total Quality Management (TQM)
3. Periodic Inventory System
4. Business Process Reengineering (BPR)
Q 1 (c) Explain the term PERT & CPM with context to Project Management. Give the example
of projects where they would be applicable. (04)
Q 2 (a) Discuss the strategies to adjust capacity and manage demand along with examples. (07)
Q 2 (b) What is EOQ? Explain how order quantity is determined using the basic Economic Order
Quantity Model. (07)
OR
Q 2 (b) As a project manager of a large petrochemical refinery, how will you select the
appropriate location of a plant? Discuss various factors affecting your decision. (07)
Q 3 (a) What do you mean by Six Sigma? Explain the various analytical tools associated with
Six Sigma. (07)
Q 3 (b) The Basic Block Company needs to produce 4000 boxes of blocks per 40 hour week to
meet the upcoming holiday demand. The process of making blocks can be broken down
into six work elements. The precedence and time requirements for each element are as
follows. Draw and label a precedence diagram for the production process. Set up a
balanced assembly line and calculate the efficiency of the line. (07)
Work Element Precedence Performance Time (Min)
A - 0.10
B A 0.40
C A 0.50
D - 0.20
E C,D 0.60
F B,E 0.40
OR
Q 3 (a) Explain the different types of layout. Additionally differentiate between product and
process layout. (07)
Q 3 (b) I-75 Discount Carpet manufactures Cascade Carpet, which it sells in its adjoining
showroom store near the interstate. Estimated annual demand is 20000 yards of carpet
with an annual carrying cost of $2.75 per yard. The manufacturing facility operates the
same 360 days the store is open and produces 400 yards of carpet per day. The cost of
setting up the manufacturing process for the production run is $720. Determine the
optimal order size, total inventory cost, length of the time to receive an order, and
maximum inventory level. (07)
Q 4 (a) Discuss material handling principles and classify material handling equipments. (07)
Q 4 (b) The following table provides the information necessary to construct a project network
and project crash data
Page 3 of 5
Activity Predecessor Activity Time (Weeks) Activity Cost ($)
Normal Crash Normal Crash
A - 16 8 2000 4000
B - 14 9 1000 1800
C A 8 6 500 700
D A 5 4 600 1300
E B 4 2 1500 3000
F B 6 4 800 1600
G C 10 7 3000 4500
H D,E 15 10 5000 8000
Construct the project network, and crash the network so G and H complete at the same
time of 22 weeks. Also calculate the total crash cost. (07)
OR
Q 4 (a) What is Statistical Process Control (SPC) in Quality Management? Explain the difference
between attribute control charts and variable control charts. Elaborate with examples how
SPC is applied in case of services. (07)
Q 4 (b) Differentiate between production and operation. Additionally explain in detail the
objectives and functions of production planning and control. (07)
Q 5 The Shanghai Textile Mill was inspected and found to be in violation of a number of safety
regulations. The inspectors ordered the mill to alter some existing machinery to make it safe
and relocate some machinery to make safer passages and unobstructed entrances and exits.
The inspector gave the mill only 35 weeks to make the changes; if the changes were not
made by then, the mill would be fined $300000. The mill determined the activities in PERT
network that would have to be completed and then estimated the indicated activity times, as
shown in the table below:
Activity Description Predecessor
Time (Weeks)
a m b
A Order new machine - 1 2 4
B Plan new layout - 2 5 8
C Deter safety changes - 1 3 7
D Receive equipments A 5 10 23
E Hire new employees A 3 7 12
F Make plant alterations B 10 15 18
G Make change in existing machine C 7 9 11
H Train new employees D,E 2 4 7
I Install new equipments D,E,F 2 4 6
J Relocate old machine D,E,F,G 4 7 10
K Conduct employee safety H,I,J 2 3 4
Construct the PERT network and find the following
a. Expected Activity Time
b. Earliest / Latest Times / Slack
c. Critical Path
d. Expected project duration and variance
e. The probability that mill would be fined $300000 (14)
OR
Page 4 of 5
Q 5 Read the following case and answer the question below (14)
Steve Jobs and Apple
Late Steve Jobs completed the education only till high school when he dropped out from Reed
College, Oregon. Another drop out from University of California at Berkley was Stephen
Wozniak, who started working for Hewlett-Packard (HP) and came in contact with a summer
intern there ? Jobs. Wozniak was an engineering wizard, who was influenced by Jobs to quit his
job at HP and start a new venture. Thus Apple Computer Corporation was founded by Jobs
alongwith Wozniak in 1976 in his car garbage. At that time, nobody had imagined that large
computers hitherto confined to scientific installations could be configured for personal use by
individuals. The Apple computer designed and created by the duo received orders of 25 units
from the local electronics retailer and from thereon, the story of first personal computer was
started. Rest is now history.
Apple?s approach to designing new products is rather unconventional, as if symbolizing the
exotic leadership style of Jobs. If Steve?s words, ?Simplicity is the ultimate sophistication.? A
typical example is the IPod, which was designed to play the music through a miniature device
and do nothing else. The platform strategy is clearly evident in use of OSX operating system in
Macintosh, PCs, iPhone, and iPad. In fact, iPad is a natural extension of the iPhone in terms of
touch screen and other common user interfaces/applications. This promotes reusability of parts,
components, software etc., while ensuring less training on part of existing customers using Apple
Products. Future applicability of current products through cross-pollination of internal ideas and
technologies is an important aspect of Apple designs. Another facet of its approach is
?participatory design? whereby customers play an active role in design process. In the
development stages, the experiences and problems faced by a sample set of customers using a
software/product are meticulously observed. The focus then shifts to finding simple yet effective
solutions to such problems for improvising the designs. The customer involvement is ?iterative?
in nature, that is, there experiences are continually monitored to identify the scope of further
improvement. This explains the progressive release of latest versions of products, taking for
example iPhone 4 has innovative features such as video calling with Face time, retina display
with 960 by 640 resolution, HD video recording, 5 megapixel camera with LED flash, dual-mic
noise suppression, and much more. What sets Apple products apart from competition is their
aesthetic appeal. The pristine white colour almost becomes synonymous with Apple products
with ?snow white skin?, when the company introduced vibrant colours in some of its products
like iPods. This simply shows the flexibility and dynamism in Apple designs rather than getting
trapped in statics of currently successful designs. The future outlook and boldness is clearly
hallmark of Apple designs, which always leaves the competition to do lots of catching up.
Experts argue that Apple products are not radical innovations but improvisations of existing
products in the market. According to them, neither was iPod the first MP3 player nor was iPhone
the first smartphone with a touch screen. iPad was not the first tablet either. The bottom line is
that Apple not only learns from its own mistakes, but also from the competitor?s mistakes.
Apple?s mission is not to be the first but clearly to be the best.
Job?s idea of innovation in design is aptly captured by his statement below:
Page 5 of 5
?The system is that there is no system. That doesn?t mean we don?t have process. Apple is a very
disciplined company, and we have great processes. But that?s not what it?s about. Process makes
you more efficient. But innovation comes from people meeting up in the hallways or calling each
other at 10.30 am at night with a new idea, or because they realized something that shoots holes
in how we have been thinking about a problem. Its adhoc meetings of six people called by
someone who thinks he has figured out the coolest new thing ever and who wants to know what
other people think of his idea. And it comes from saying no to thousand things to make sure we
don?t get on the wrong track or try to do too much.?
a. Do you agree with Apple?s strategy of creating their iPad only in two colours- black
and white?
b. Apple?s approach to product development has been to build upon existing
technologies. Do you think it is high time that Apple started innovating new
technologies on its own?
c. When asked what consumer and market research Apple had done to guide the
development of iPad, its former CEO Late Steve Jobs replied, ?None. It isn?t the
consumer?s job to know what they want.? Do you agree with this statement from
Jobs?