1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ?VIII(NEW) EXAMINATION ? SUMMER 2019
Subject Code:2184001 Date:09/05/2019

Subject Name: PROFESSIONAL PRACTICE AND VALUATION OF
INFRASTRUCTURE

Time:10:30 AM TO 01:00 PM Total Marks: 70

Instructions:

1. Attempt all questions.

2. Make suitable assumptions wherever necessary.

3. Figures to the right indicate full marks.
MARKS
Q.1 (a) What are various types of estimate for building; give suitability of each type with
example.
03
(b) What is the use of construction cost index in estimation? Justify your view with suitable
example.

04
(c) Explain FIDIC contract conditions? Evaluate and mark the difference between FIDIC
contract conditions and state R&B contract norms.

07
Q.2 (a) Draw flowchart of preparation of detailed estimates. 03
(b) Discuss all characteristics of a ?good? contract document briefly. 04
(c) For the given plan, derive detailed estimate for
1. Concrete in foundation
2. Brickwork in foundation and
3. Brickwork in plinth level


07
OR
(c) For the given plan, derive detailed estimate.
1. Earthwork in excavation for foundation
2. Lime Concrete in foundation
3. 1
st
class Brickwork in foundation and plinth level
4. 2.5 cm Cement Concrete (CC) damp proof course
07
FirstRanker.com - FirstRanker's Choice
1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ?VIII(NEW) EXAMINATION ? SUMMER 2019
Subject Code:2184001 Date:09/05/2019

Subject Name: PROFESSIONAL PRACTICE AND VALUATION OF
INFRASTRUCTURE

Time:10:30 AM TO 01:00 PM Total Marks: 70

Instructions:

1. Attempt all questions.

2. Make suitable assumptions wherever necessary.

3. Figures to the right indicate full marks.
MARKS
Q.1 (a) What are various types of estimate for building; give suitability of each type with
example.
03
(b) What is the use of construction cost index in estimation? Justify your view with suitable
example.

04
(c) Explain FIDIC contract conditions? Evaluate and mark the difference between FIDIC
contract conditions and state R&B contract norms.

07
Q.2 (a) Draw flowchart of preparation of detailed estimates. 03
(b) Discuss all characteristics of a ?good? contract document briefly. 04
(c) For the given plan, derive detailed estimate for
1. Concrete in foundation
2. Brickwork in foundation and
3. Brickwork in plinth level


07
OR
(c) For the given plan, derive detailed estimate.
1. Earthwork in excavation for foundation
2. Lime Concrete in foundation
3. 1
st
class Brickwork in foundation and plinth level
4. 2.5 cm Cement Concrete (CC) damp proof course
07
2

Q.3 (a) Discuss the statement ?Owner agrees to pay actual cost plus an agreed % of actual cost
(to cover overhead and profit)? with reference to Cost plus percentage contracts with
suitable example.
03
(b) Write important features of ?Tender notice?. 04
(c) Explain all dispute resolution mechanisms in a contract agreement with suitable
example for each.
07
Q.4 (a) Discuss the statement ?Owner will have definite information on the resource
requirements? with reference to Lump sum contract. Justify your comments with
suitable examples.
03
(b) Discuss various reasons for rejection of a tender or all tenders. 04
(c) A three-story building standing on a plot of 800 sq. m. the plinth area of each story is
400 sq m. RCC framed structure with 70 years of future life may be assumed. A gross
rate of 1500 Rs per month is received. Workout the capitalized value of the property
on the basis of 6% net yield. For sinking fund 3% compound interest may be assumed.
Cost of land may be taken 40 Rs per sq m. Assume following outgoings:

1. Repairs at 0.5 times of gross income
2. Municipal tax at 20% of gross income
3. Property tax of 5% on gross income
4. Insurance premium of 0.5% of gross income
5. Management charges at 6% of gross income
6. Other miscellaneous charges are at 2% of gross income.

07
OR
FirstRanker.com - FirstRanker's Choice
1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ?VIII(NEW) EXAMINATION ? SUMMER 2019
Subject Code:2184001 Date:09/05/2019

Subject Name: PROFESSIONAL PRACTICE AND VALUATION OF
INFRASTRUCTURE

Time:10:30 AM TO 01:00 PM Total Marks: 70

Instructions:

1. Attempt all questions.

2. Make suitable assumptions wherever necessary.

3. Figures to the right indicate full marks.
MARKS
Q.1 (a) What are various types of estimate for building; give suitability of each type with
example.
03
(b) What is the use of construction cost index in estimation? Justify your view with suitable
example.

04
(c) Explain FIDIC contract conditions? Evaluate and mark the difference between FIDIC
contract conditions and state R&B contract norms.

07
Q.2 (a) Draw flowchart of preparation of detailed estimates. 03
(b) Discuss all characteristics of a ?good? contract document briefly. 04
(c) For the given plan, derive detailed estimate for
1. Concrete in foundation
2. Brickwork in foundation and
3. Brickwork in plinth level


07
OR
(c) For the given plan, derive detailed estimate.
1. Earthwork in excavation for foundation
2. Lime Concrete in foundation
3. 1
st
class Brickwork in foundation and plinth level
4. 2.5 cm Cement Concrete (CC) damp proof course
07
2

Q.3 (a) Discuss the statement ?Owner agrees to pay actual cost plus an agreed % of actual cost
(to cover overhead and profit)? with reference to Cost plus percentage contracts with
suitable example.
03
(b) Write important features of ?Tender notice?. 04
(c) Explain all dispute resolution mechanisms in a contract agreement with suitable
example for each.
07
Q.4 (a) Discuss the statement ?Owner will have definite information on the resource
requirements? with reference to Lump sum contract. Justify your comments with
suitable examples.
03
(b) Discuss various reasons for rejection of a tender or all tenders. 04
(c) A three-story building standing on a plot of 800 sq. m. the plinth area of each story is
400 sq m. RCC framed structure with 70 years of future life may be assumed. A gross
rate of 1500 Rs per month is received. Workout the capitalized value of the property
on the basis of 6% net yield. For sinking fund 3% compound interest may be assumed.
Cost of land may be taken 40 Rs per sq m. Assume following outgoings:

1. Repairs at 0.5 times of gross income
2. Municipal tax at 20% of gross income
3. Property tax of 5% on gross income
4. Insurance premium of 0.5% of gross income
5. Management charges at 6% of gross income
6. Other miscellaneous charges are at 2% of gross income.

07
OR
3
(c) In a plot of land costing 20,000, a new construction of building is done at a cost of
80,000 Rs. The building consist of 4 flats. The owner expect 8% return on the cost of
construction and 5% return on cost of land. Consider sinking fund of 4% interest basis
for a future life of 60 years. Also annual repairs cost at 1% of construction. Other
outgoing including taxes at 30% of the return on the building. Calculate the standard
rent per month for each flat of the building.
07
Q.5 (a) What do you mean by scrap value, salvage value, market value & book value? 03
(b) What do you mean by Specifications; Explain with some suitable examples? 04
(c) Derive the cost of reinforcement in beam per unit length with your comments. 07
OR
(c) Find labor (Skilled / Semi Skilled / Unskilled) productivity for concreting of column
per meter run.
07

*************