BE - SEMESTER ?VII (NEW) EXAMINATION ? WINTER 2018
Subject Code: 2170610 Date: 29/11/2018

Subject Name: Professional Practices & Valuation

Time: 10:30 AM TO 01:00 PM Total Marks: 70

Instructions:

1. Attempt all questions.

2. Make suitable assumptions wherever necessary.

3. Figures to the right indicate full marks.


Q.1 (a) Discuss accuracy criteria for concrete. 03
(b) Define specification. What are the purpose of writing. 04
(c) Calculate the following quantities for residential quarters shown in drawing.
( refer fig 1 ) [1] Excavation for Foundation [2] Brick bate cement concrete
{1:4:8} for foundation[3] Brick masonry up to plinth C.M {1:6}
07

Q.2 (a) Explain in detail various reasons for termination of contract. 03
(b) Define rate analysis. How to fixed rate per unit of item in rate analysis? 04
(c) Discuss measurement method for road work. 07
OR
(c) Calculate the following:
1. No. of bricks required for 1 cu. m. brick work.
2. No. of cement bags for 1 cu.m brick work in cement mortar 1:4
07

Q.3 (a) Define following terms ? Estimate, Contingencies, Spot Item 03
(b) Differentiate between Estimation & Valuation 04
(c) Explai Explain the following types of engineering contracts ?( 1) Item Rate Contract (2)
BOT percentage rate of contract ( 3) Lump Sum Contract
07
OR
Q.3 (a) What do you mean by value ? State the purposes of Valuation. 03
(b) Enlist different types of tenders & explain anyone them. 04
(c) Write detail specifications for Earthwork in excavation in foundation. 07
Q.4 (a) Write short note on Schedule of rates (S.O.R) 03
(b) Enlist the various methods of valuation and explain any one in detail. 04
(c) Define tender and draft a typical tender notice for civil engineering works. 07
OR
Q.4 (a) Discuss various conditions of contract. 03
(b) Write difference between : 'Depreciation and Obsolescnce.' 04
(c) A machine is purchased for Rs-1,00,000. Assuming its life 12 years its
10%salvage value. Calculate the amount of depreciation at the end of third
year in a tabular form by using following methods ?( 1) Straight Line Method
(2) Constant Percentag Method.
07

Q.5 (a) Explain : 1.Tender fee, 2. Earnest money deposition 03
(b) Explain in brief about work charge establishment. 04
(c) How would you determine value of the property using rental method of
valuation? Enumerate its advantages and limitations.
07
OR

Q.5 (a) Write formulas for the following: (1) Area of Segment of Circle (2) Area of
ellipse (3) Curved surface area of cylinder
03
www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
FirstRanker.com - FirstRanker's Choice
www.FirstRanker.com
1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ?VII (NEW) EXAMINATION ? WINTER 2018
Subject Code: 2170610 Date: 29/11/2018

Subject Name: Professional Practices & Valuation

Time: 10:30 AM TO 01:00 PM Total Marks: 70

Instructions:

1. Attempt all questions.

2. Make suitable assumptions wherever necessary.

3. Figures to the right indicate full marks.


Q.1 (a) Discuss accuracy criteria for concrete. 03
(b) Define specification. What are the purpose of writing. 04
(c) Calculate the following quantities for residential quarters shown in drawing.
( refer fig 1 ) [1] Excavation for Foundation [2] Brick bate cement concrete
{1:4:8} for foundation[3] Brick masonry up to plinth C.M {1:6}
07

Q.2 (a) Explain in detail various reasons for termination of contract. 03
(b) Define rate analysis. How to fixed rate per unit of item in rate analysis? 04
(c) Discuss measurement method for road work. 07
OR
(c) Calculate the following:
1. No. of bricks required for 1 cu. m. brick work.
2. No. of cement bags for 1 cu.m brick work in cement mortar 1:4
07

Q.3 (a) Define following terms ? Estimate, Contingencies, Spot Item 03
(b) Differentiate between Estimation & Valuation 04
(c) Explai Explain the following types of engineering contracts ?( 1) Item Rate Contract (2)
BOT percentage rate of contract ( 3) Lump Sum Contract
07
OR
Q.3 (a) What do you mean by value ? State the purposes of Valuation. 03
(b) Enlist different types of tenders & explain anyone them. 04
(c) Write detail specifications for Earthwork in excavation in foundation. 07
Q.4 (a) Write short note on Schedule of rates (S.O.R) 03
(b) Enlist the various methods of valuation and explain any one in detail. 04
(c) Define tender and draft a typical tender notice for civil engineering works. 07
OR
Q.4 (a) Discuss various conditions of contract. 03
(b) Write difference between : 'Depreciation and Obsolescnce.' 04
(c) A machine is purchased for Rs-1,00,000. Assuming its life 12 years its
10%salvage value. Calculate the amount of depreciation at the end of third
year in a tabular form by using following methods ?( 1) Straight Line Method
(2) Constant Percentag Method.
07

Q.5 (a) Explain : 1.Tender fee, 2. Earnest money deposition 03
(b) Explain in brief about work charge establishment. 04
(c) How would you determine value of the property using rental method of
valuation? Enumerate its advantages and limitations.
07
OR

Q.5 (a) Write formulas for the following: (1) Area of Segment of Circle (2) Area of
ellipse (3) Curved surface area of cylinder
03
www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
www.FirstRanker.com
2
(b) Compare revised estimate and supplementary estimate 04
(c) Discuss mode of payment to the contractor. How the first and final bill, running
or interim bills are paid to contractor?
07


*******

www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
FirstRanker.com - FirstRanker's Choice
www.FirstRanker.com
1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ?VII (NEW) EXAMINATION ? WINTER 2018
Subject Code: 2170610 Date: 29/11/2018

Subject Name: Professional Practices & Valuation

Time: 10:30 AM TO 01:00 PM Total Marks: 70

Instructions:

1. Attempt all questions.

2. Make suitable assumptions wherever necessary.

3. Figures to the right indicate full marks.


Q.1 (a) Discuss accuracy criteria for concrete. 03
(b) Define specification. What are the purpose of writing. 04
(c) Calculate the following quantities for residential quarters shown in drawing.
( refer fig 1 ) [1] Excavation for Foundation [2] Brick bate cement concrete
{1:4:8} for foundation[3] Brick masonry up to plinth C.M {1:6}
07

Q.2 (a) Explain in detail various reasons for termination of contract. 03
(b) Define rate analysis. How to fixed rate per unit of item in rate analysis? 04
(c) Discuss measurement method for road work. 07
OR
(c) Calculate the following:
1. No. of bricks required for 1 cu. m. brick work.
2. No. of cement bags for 1 cu.m brick work in cement mortar 1:4
07

Q.3 (a) Define following terms ? Estimate, Contingencies, Spot Item 03
(b) Differentiate between Estimation & Valuation 04
(c) Explai Explain the following types of engineering contracts ?( 1) Item Rate Contract (2)
BOT percentage rate of contract ( 3) Lump Sum Contract
07
OR
Q.3 (a) What do you mean by value ? State the purposes of Valuation. 03
(b) Enlist different types of tenders & explain anyone them. 04
(c) Write detail specifications for Earthwork in excavation in foundation. 07
Q.4 (a) Write short note on Schedule of rates (S.O.R) 03
(b) Enlist the various methods of valuation and explain any one in detail. 04
(c) Define tender and draft a typical tender notice for civil engineering works. 07
OR
Q.4 (a) Discuss various conditions of contract. 03
(b) Write difference between : 'Depreciation and Obsolescnce.' 04
(c) A machine is purchased for Rs-1,00,000. Assuming its life 12 years its
10%salvage value. Calculate the amount of depreciation at the end of third
year in a tabular form by using following methods ?( 1) Straight Line Method
(2) Constant Percentag Method.
07

Q.5 (a) Explain : 1.Tender fee, 2. Earnest money deposition 03
(b) Explain in brief about work charge establishment. 04
(c) How would you determine value of the property using rental method of
valuation? Enumerate its advantages and limitations.
07
OR

Q.5 (a) Write formulas for the following: (1) Area of Segment of Circle (2) Area of
ellipse (3) Curved surface area of cylinder
03
www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
www.FirstRanker.com
2
(b) Compare revised estimate and supplementary estimate 04
(c) Discuss mode of payment to the contractor. How the first and final bill, running
or interim bills are paid to contractor?
07


*******

www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
www.FirstRanker.com
3

Figure 1
www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
FirstRanker.com - FirstRanker's Choice

This post was last modified on 20 February 2020