Roll No. Total No. of Pages : 02
Total No. of Questions : 09
--- Content provided by FirstRanker.com ---
B.Tech.(CE) (2012 to 2017) (Sem.-6)PROFESSIONAL PRACTICE
Subject Code : BTCE-605
M.Code : 71086
Time : 3 Hrs. Max. Marks : 60
--- Content provided by FirstRanker.com ---
INSTRUCTION TO CANDIDATES :
- SECTION-A is COMPULSORY consisting of TEN questions carrying TWO marks each.
- SECTION-B contains FIVE questions carrying FIVE marks each and students have to attempt any FOUR questions.
- SECTION-C contains THREE questions carrying TEN marks each and students have to attempt any TWO questions.
SECTION-A
--- Content provided by FirstRanker.com ---
- Write briefly :
- Name various types of roofs.
- What are overhead costs?
- List various factors upon which rates of particular item of work depends upon.
- What do you mean by out turn work?
- What do you mean by earnest money?
- What do you mean by Security earnest money?
- Define Work Order.
- What are Unliquidated damages?
- What is subsidiary cash book?
- Define Temporary Imprest.
--- Content provided by FirstRanker.com ---
--- Content provided by FirstRanker.com ---
SECTION-B
- Estimate the material and cost of foundation with 40mm gauge brick ballast unit 1 cum for 10 cum.
- Prepare a detailed estimate of the Madras Terrace Roof of a room of 3 x 4.5m in size. The beams are of sal wood 8x16 cm size spaced 45 cm centre to centre. The ceiling shall be finished with 12mm cement plaster of 1:3 proportions. Concealed faces of wooden beams shall be painted with two coats of coal tar and the exposed faces shall be painted with two coats of painting over one coat of priming?
- Give detailed specifications for Earthwork in excavation in foundation.
- What is a contract document? What does it contain? Explain.
- What are the various particulars given in the tender notice? Explain in detail.
--- Content provided by FirstRanker.com ---
SECTION-C
- What are the various categories into which transactions of Public Works offices are grouped? Explain in detail.
- What are the various rules and methods of measurement followed for preparation of the estimates and bills of quantities for Brickwork?
- Enumerate detailed specifications of Road work.
--- Content provided by FirstRanker.com ---
NOTE : Disclosure of Identity by writing Mobile No. or Making of passing request on any page of Answer Sheet will lead to UMC against the Student.
--- Content provided by FirstRanker.com ---
This download link is referred from the post: PTU B.Tech Question Papers 2020 March (All Branches)