PROJECT MANAGEMENT
Time: 3hours
--- Content provided by FirstRanker.com ---
Max.Marks:75
Note: This question paper contains two parts A and B.
Part A is compulsory which carries 25 marks. Answer all questions in Part A. Part B consists of 5 Units. Answer any one full question from each unit. Each question carries 10 marks and may have a, b, c as sub questions.
PART - A 5 × 5 Marks = 25
-
Discuss tools and techniques of Project Management? [5]
--- Content provided by FirstRanker.com ---
-
Write a note on Social Cost Benefit Analysis. [5]
-
Discuss different Project Evaluation Techniques. [5]
-
Explain Agile Project Management. [5]
-
Write short notes on participative management in Project. [5]
--- Content provided by FirstRanker.com ---
PART - B 5 × 10 Marks = 50
--- Content provided by FirstRanker.com ---
-
Discuss the need and benefits of Project Management and brief on project management in different sectors. [10]
OR
-
Explain the areas to be examined for a cement plant during definition phase of project life cycle. [10]
-
-
What are the objectives of Project Appraisal?
-
Describe the feasibility report for establishing a new project. [5+5]
OR
--- Content provided by FirstRanker.com ---
-
-
Discuss various steps involved in Project Management Planning process with an illustration. [10]
-
Explain the methods of project evaluation. Also write how a project is audited. [10]
OR
--- Content provided by FirstRanker.com ---
-
Discuss the concept of cost estimation and cost improvement in project finance. [10]
-
Explain the networking process during uncertainty and risk in scheduling a project. [10]
OR
--- Content provided by FirstRanker.com ---
-
Define Project Execution? What are the various techniques in monitoring and controlling? [10]
-
Enumerate the pitfalls of ineffective project team and brief on stress management. [10]
OR
--- Content provided by FirstRanker.com ---
-
Describe the methods of resolving conflicts in project management. [10]