Download AKTU B-Tech 5th Sem 2015-2016 Machine Design I Eme 501 Nme 501 Question Paper

Download AKTU (Dr. A.P.J. Abdul Kalam Technical University (AKTU), formerly Uttar Pradesh Technical University (UPTU) B-Tech 5th Semester (Fifth Semester) 2015-2016 Machine Design I Eme 501 Nme 501 Question Paper

This post was last modified on 29 January 2020

AKTU B-Tech Last 10 Years 2010-2020 Previous Question Papers || Dr. A.P.J. Abdul Kalam Technical University


II B.Tech I Semester Regular Examinations, November 2018

SURVEYING

(Civil Engineering)

Time: 3 hours Max. Marks: 70

Note: 1. Question Paper consists of two parts (Part-A and Part-B)

2. Answer ALL the question in Part-A

--- Content provided by⁠ FirstRanker.com ---

3. Answer any FOUR Questions from Part-B

PART-A

1. a) What are the uses of surveying? [2M]

b) Define orientation. [2M]

c) What is meant by face left and face right observations? [2M]

d) Define contour interval and horizontal equivalent. [2M]

--- Content provided by‌ FirstRanker.com ---

e) What are the methods of determining areas? [2M]

f) Define sounding. [2M]

g) What is meant by remote sensing? [2M]

PART-B

2. a) Explain the classification of surveying. [7M]

b) A tape of nominal length 30m was used to measure a line. The measured length was 245.86m. The standard length of the tape was 30.03m. Find the correct length of the line. [7M]

--- Content provided by‍ FirstRanker.com ---

3. a) Explain about the temporary adjustments of a transit theodolite. [7M]

b) The following bearings were observed with a compass:

Line Fore Bearing Back Bearing
AB S 45°30’ E N 46°0’ W
BC S 60°0’ E N 60°0’ W
CD N 5°30’ W S 5°30’ E
DE N 65°0’ E S 64°0’ W
EA N 30°30’ E S 30°30’ W

At what stations is local attraction suspected? Find the correct bearings of the lines. [7M]

4. a) Explain about different methods of leveling. [7M]

b) The following consecutive readings were taken with a level and a 3m leveling staff on continuously sloping ground at a common interval of 20m. 0.685, 1.455, 2.325, 0.375, 1.030, 1.925, 2.845, 0.565, 1.375, 2.130. The Reduced Level (RL) of the first point was 80.750m. Calculate the Reduced Levels of the remaining points and also the gradient of the line. [7M]

--- Content provided by​ FirstRanker.com ---

5. a) Explain about the characteristics of contours. [7M]

b) The area of the plan of an excavation is 50 sq. cm. The depths at the corners of the rectangles, 10m x 10m, were measured and found to be as follows:

A B C D
1 2.0 3.0 4.0 2.5
2 3.5 4.5 5.0 3.0
3 4.5 5.5 6.0 4.0
4 3.0 4.0 4.5 2.5

Calculate the volume of excavation by (i) Trapezoidal formula and (ii) Prismoidal formula. The scale of the plan is 1cm = 10m. [7M]

6. a) Derive an expression for calculating the area enclosed by a traverse. [7M]

b) Explain about different methods of plane table surveying. [7M]

--- Content provided by​ FirstRanker.com ---

7. a) What is meant by GPS? Explain about different segments of GPS. [7M]

b) Write short notes on: [7M]

i) EDM

ii) Total station