FirstRanker Logo

FirstRanker.com - FirstRanker's Choice is a hub of Question Papers & Study Materials for B-Tech, B.E, M-Tech, MCA, M.Sc, MBBS, BDS, MBA, B.Sc, Degree, B.Sc Nursing, B-Pharmacy, D-Pharmacy, MD, Medical, Dental, Engineering students. All services of FirstRanker.com are FREE

📱

Get the MBBS Question Bank Android App

Access previous years' papers, solved question papers, notes, and more on the go!

Install From Play Store

Download AKTU B-Tech 8th Sem 2016-17 ECE053 Water Resources Systems Question Paper

Download AKTU (Dr. A.P.J. Abdul Kalam Technical University (AKTU), formerly Uttar Pradesh Technical University (UPTU) B-Tech 8th Semester (Eight Semester) 2016-17 ECE053 Water Resources Systems Question Paper

This post was last modified on 30 January 2020

AKTU B-Tech Last 10 Years 2010-2020 Previous Question Papers || Dr. A.P.J. Abdul Kalam Technical University


Firstranker's choice

FirstRanker.com

Printed Pages : 2

--- Content provided by‍ FirstRanker.com ---

Roll No.

B.TECH.

FirstRanker.com

ECE053

THEORY EXAMINATION (SEM–VIII) 2016-17

--- Content provided by‍ FirstRanker.com ---

WATER RESOURCES SYSTEMS

Time: 3 Hours

Max. Marks : 100

Note: Be precise in your answer. In case of numerical problem assume data wherever not provided.

SECTION-A

--- Content provided by‌ FirstRanker.com ---

  1. Attempt all parts in short. (2×10=20)

    1. Explain the term stochastic modeling.
    2. Define the term 'system analysis'?
    3. Hydrologic measurements are subject to errors. Write the types of these errors.
    4. A LP problem has all equality constraints. The number of constraints is the same as the number of decision variables. How does the solution change with a change in the coefficients (of decision variables) in the objective function?
    5. --- Content provided by‌ FirstRanker.com ---

    6. What is a rating curve? Write the equation of a rating curve.
    7. Write four physical parameters of water quality?
    8. What is an objective function?
    9. Define optimal control problems.
    10. What are decision variables?
    11. --- Content provided by‌ FirstRanker.com ---

    12. What is the reservoir routing?

SECTION-B

  1. Attempt any five of the following : (10×5=50)

    1. What do you mean by the 'system'? Classify the systems and explain them.
    2. --- Content provided by⁠ FirstRanker.com ---

    3. With reference to a multipurpose project, define the terms: separable costs, joint costs, distributed costs and specific costs.
    4. What is Lagrange multiplier method? How this is used in planning of water resources systems?
    5. What do you understand by simulation? Under what conditions, simulation models are better than optimization models and in what conditions, optimization models are better than simulation models?
    6. A dam is proposed across a river in Himalayas. It will supply water for irrigation. List and explain possible beneficial and harmful environmental consequences of the project.
    7. Explain the following terms :
      1. Plan selection
      2. --- Content provided by⁠ FirstRanker.com ---

      3. Plan formulation
      4. Sensitivity Analysis
    8. Differentiate weighting method and constraint method of formulation of a multi objective planning problem. Explain any one of them in detail.
    9. What is system decomposition? Explain in detail major types of decompositions.
    10. --- Content provided by‍ FirstRanker.com ---

SECTION-C

  1. Attempt any two of the following: (15×2=30)

    1. Explain the following in detail:
      1. Total, average and marginal cost curves
      2. Production and objective functions
      3. --- Content provided by⁠ FirstRanker.com ---

    FirstRanker.com

    Firstranker's choice

    FirstRanker.com

      1. Discount factors and its types.
      2. --- Content provided by⁠ FirstRanker.com ---

    FirstRanker.com

  2. Water is supplied from a project for two types of users: rural and urban. The benefits to rural community are given by B1 = 30y1 – 1.5y1² and those to urban community are given by B2 = 10y2 - (y2²/2) .If the total cost of the project is C = 8 + 2y, where y is the aggregate demand, determine the optimum level of water supply. Also, determine the corresponding components of rural and urban water supply levels.
  3. Solve the following LP problem by simplex method:

    Maximize z = X1 + X2

    --- Content provided by​ FirstRanker.com ---

    Subject to x1 + 3x2 = 6

    4x1 + 3x2 = 12

    3x1-x2 = 36

    X1, X2 = 0