Roll FirstRanker.com
B.TECH.
--- Content provided by FirstRanker.com ---
THEORY EXAMINATION (SEM–VIII) 2016-17
SOFTWARE PROJECT MANAGEMENT
Time: 3 Hours
Max. Marks : 100
Note: Be precise in your answer. In case of numerical problem assume data wherever not provided.
--- Content provided by FirstRanker.com ---
SECTION – A
- Attempt the following: 10 x 2 = 20
- Explain SPM Framework.
- Explain the term Project Scope with example.
- Enumerate the authorities of a Project Manager.
- Compare PERT and CPM.
- Write the steps of software development.
- Explain cost benefit Analysis.
- What is meant by Software configuration management?
- Explain unit testing and system testing.
- What do you mean by Code Inspection?
- What is the difference between change control and version control?
--- Content provided by FirstRanker.com ---
--- Content provided by FirstRanker.com ---
SECTION – B
- Attempt any five of the following questions: 5 x 10 = 50
- Give the Overview of the stepwise planning of the software project Development.
- What do you mean by Work Break down Structure in context to software project and product? Discuss with example.
- Explain all types of Risks which occur during software development.
- Define various type of testing strategies with example
- What do you understand by Verification and validation? Explain their difference with example.
- Write COCOMO model in detail.
- Explain project monitoring and controlling process. Explain different dimensions of project monitoring and control.
- Discuss the different steps of preparing the schedule. What are the Inputs and outputs required by Schedule?
--- Content provided by FirstRanker.com ---
--- Content provided by FirstRanker.com ---
SECTION - C
- Attempt any two of the following questions: 2 x 15 = 30
- What do you understand by “Earned Value Analysis”? Discuss the following Progress indicators:
- Cost Variance
- Schedule performance Index(SPI)
- Cost Performance Index (CPI)
--- Content provided by FirstRanker.com ---
- Explain the following:
- Software Quality Attributes
- SEI-CMM
- Explain various types of software project management Tools.
--- Content provided by FirstRanker.com ---
- What do you understand by “Earned Value Analysis”? Discuss the following Progress indicators:
--- Content provided by FirstRanker.com ---
This download link is referred from the post: AKTU B-Tech Last 10 Years 2010-2020 Previous Question Papers || Dr. A.P.J. Abdul Kalam Technical University