PG-1001
II Semester M.B.A. Degree Examination, June/July 2015
(2007-08 Scheme)
--- Content provided by FirstRanker.com ---
Management
2.6 : QUANTITATIVE METHODS AND OPERATIONS RESEARCH
Time : 3 Hours Max. Marks : 75
Instruction : Scientific calculators are allowed.
SECTION-A
--- Content provided by FirstRanker.com ---
Answer any six questions. Each question carries two marks. (6x2=12)
- a) Define linear programming problem.
- b) What is unbalanced assignment?
- c) What is group replacement?
- d) What are the significance of VAM ?
- e) Define critical path.
- f) What is simulation ?
- g) What do you mean by degeneracy ?
- h) Mention the assumptions of EOQ model.
--- Content provided by FirstRanker.com ---
SECTION-B
--- Content provided by FirstRanker.com ---
Answer any three questions. Each question carries 8 marks. (3x8=24)
- “Operation research replaces management by personality”. Discuss.
- What is sequencing problem ? Give its essential characteristics.
- A company for one of the z-class items, placed 10 orders each of size 300 in a year. Given ordering cost Rs. 750, holding cost 45%, cost per unit Rs. 35. Find out the loss to the company in not operating scientific inventory policy.
- There are 6 jobs each of which must go through machines A, B and C in the order ABC processing time (in hours) given in the following table.
Job 1 2 3 4 5 6 Machine A 8 3 7 10 5 4 Machine B 6 4 8 2 1 7 Machine C 8 7 6 9 10 9 - Solve the problem of assignment for the given table to maximise the sales.
A B C D E 1 32 38 40 28 40 2 40 24 28 21 36 3 41 27 33 30 37 4 22 38 41 36 36 5 29 33 40 35 39
--- Content provided by FirstRanker.com ---
SECTION-C
Answer any two of the following : (2x12=24)
- Explain the different models of O.R. How are these models useful in day to day operation ?
- Use the simplex method to solve the following L.P.P. Maximize Z = 3x1 + 5x2 + 4x3
--- Content provided by FirstRanker.com ---
S.T. 2x1 + 3x2 = 8
2x2 + 5x3 = 10
3x1 + 2x2 + 4x3 = 15
and x1, x2, x3 = 0. - Simulation of demand forecasting.
--- Content provided by FirstRanker.com ---
A dealer sells a particular model of washing machine for which the probability distribution of daily demand is as given below.Demand/Week 20 30 35 40 45 50 Probability 0.05 0.25 0.20 0.25 0.10 0.15
SECTION-D
10. Case study compulsory : (1x15=15)
Below given table has a list of activities and time estimates.
Activity | Predecessor | Activity to | t m | tp |
---|---|---|---|---|
A | - | 2 | 4 | 10 |
B | - | 3 | 4 | 5 |
C | A | 1 | 2 | 3 |
D | A | 4 | 6 | 14 |
E | B | 4 | 5 | 12 |
F | C | 3 | 4 | 6 |
G | D, E | 1 | 1 | 8 |
- Construct a PERT network and determine the critical path.
- What is the probability that the project shall be complete within a period of 15 weeks ?
- What is the probability that the project is completed within 10 and 18 weeks ?
--- Content provided by FirstRanker.com ---
Visit FirstRanker.com for more information.
--- Content provided by FirstRanker.com ---
This download link is referred from the post: BU MBA Last 10 Years 2010-2020 Previous Question Papers || Bangalore University (1st, 2nd, 3rd & 4th Sem)