Download GTU (Gujarat Technological University Ahmedabad) B.Tech/BE (Bachelor of Technology/ Bachelor of Engineering) 2020 Winter 7th Sem 2174002 Construction Planning And Management Previous Question Paper
Enrolment No.
GUJARAT TECHNOLOGICAL UNIVERSITY
BE- SEMESTER?VII (NEW) EXAMINATION ? WINTER 2020
Subject Code:2174002
Date:21/01/2021
Subject Name:Construction Planning & Management
Time:10:30 AM TO 12:30 PM
Total Marks: 56
Instructions:
1. Attempt any FOUR questions out of EIGHT questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
MARKS
Q.1 (a) What are the construction management functions during the construction
03
phase of a project?
(b) Explain in brief: various life cycle phases of a typical construction
04
project.
(c) Explain the Project Work Breakdown Structure (WBS) in detail. Also
07
draw a typical WBS for a `Shopping Mall Construction Project'.
Q.2 (a) Explain various types of activity Floats in network diagram. How they are
03
evaluated?
(b) Draw a network diagram (AOA) for the following activities in a project.
04
Activities
IPA
Labors/day Days(duration
A
--
5
3
B
--
8
3
C
A
7
5
D
B
6
2
E
C, D
5
2
(c) Draw a network (AOA) from the following activities and find critical
07
path and duration of project.
Activities
Duration Activities Duration
(Days)
(Days)
1-2
5
5-9
3
1-3
8
6-10
5
2-4
6
7-10
4
2-5
4
8-11
9
2-6
4
9-12
2
3-7
5
10-12
4
3-8
3
11-13
1
4-9
1
12-13
1
Q.3 (a) Briefly outline the concept of various management techniques/tools for
04
scheduling construction projects. Mention the suitability of each.
(b) Enlist the major potential risk areas of a Construction site.
03
(c) Convert the following CPM network in to AON network.
07
1
Q.4 (a) What are the limitations of the bar chart?
03
(b) Prepare a Health and Safety plan (HS plan) for a typical construction site 04
for a contractor to bid in pre-tendering process.
(c) Draw precedence diagram for the following data and find out critical path 07
and various floats. Lag/Lead relations are for a particular logical relation
is given in brackets. Where ever explicit relations are not mentioned, it is
F-S relations with zero lag/lead.
Activity
A
B
C
D
E
F
G
H
Predecessor - A[FS(1)] B B[SS(2)] D D,E E F[FF(4)],G
Duration
4
6
5
6
3
4
3
5
Q.5 (a) Enlist the cost associated for establishment of a typical construction site.
03
(b) How resource levelling and resource allocation are different? Enlist the
04
general rules to be followed in resource levelling problems.
(c) A network is given below for a project. At the end of 10 days, following
07
information are available from site on the project status. Draw an updated
network diagram using status report:
E
6
B
G
A
8
4
C
F
K
3
5
3
3
H
D
6
3
Activity D takes 6 days to finish.
Activity F takes 5 more days to complete.
It is expected that it will take total 15 days to finish activity B.
Activity H cannot start until day 17 because of the delay of
material.
Q.6 (a) What are the typical responsibilities of a contractor at a construction site?
03
(b) In the Q.2(b) network, allocate the resources based on the early start and
04
late finish times of the network.
2
(c) A project consist of 8 activities of the following time estimates. Find the
07
probability that the project will be completed in 30 weeks or less.
Activity
IPA
Most
Most likely
Pessimistic
Optimistic
time
time
time
A
--
2
4
12
B
--
10
12
26
C
A
8
9
10
D
A
10
15
20
E
A
7
7.5
11
F
B,C
9
9
9
G
D
3
3.5
7
H
E,F,G
5
5
5
Q.7 (a) Explain the following terms:
03
1. Actual cost of the work performed (ACWP)
2. Budgeted cost of the work scheduled (BCWS)
3. Budgeted cost of the work performed (BCWP)
(b) Explain central limit theorem and how it is used in PERT problems.
04
(c) PERT Data for a project is given. Calculate the completion time of
07
project with 50% probability.
Q.8 (a) Explain the following in terms of Variance analysis:
03
1. Cost Variance
2. % Cost Overrun / Underrun
3. % Time Overrun
3
(b) One project consist of 5 units requiring 7 activities. Using line of balance
04
method, schedule the project. (Consider no of gang as one for all the
activities.)
Activity
Duration (days)
A
3
B
2
C
4
D
3
E
2
F
3
G
1
(c) The table given gives the data about duration and costs of various activity
07
of network shown in figure.
Activity
Normal
Normal
Crash
Crash
Duration
cost (Rs.)
Duration
Cost (Rs.)
(Weeks)
(Weeks)
1-2
5
4000
3
12000
2-3
6
3000
3
7500
2-4
8
3600
6
6000
3-4
5
5000
3
10000
The project overhead cost are Rs. 1500 per week. Find the optimum
duration and the cost associated with it. Also, show the least cost and
duration graphically.
*************
4
5