1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ? VIII (New) EXAMINATION ? WINTER 2019
Subject Code: 2182506 Date: 25/11/2019

Subject Name: Managing Projects
Time: 02:30 PM TO 05:00 PM Total Marks: 70

Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.


MARKS

Q.1 (a) Explain scope, schedule and cost in reference to project
management.
03
(b) Explain guidelines for construction of network diagram.

04
(c) Differentiate two methods: CPM and PERT with its application 07

Q.2 (a) Draw the AOA network for the following project:
Activity A B C D E F G H
Predecessor - - A B A C,D C,D,E F

03
(b) Explain budget uncertainty in project management. 04
(c) Explain project manager?s role and responsibility in project. 07
OR
(c) A project schedule has the following characteristics
Activity A B C D E F
Predecessor - A B A D C,E
Duration(week) 5 6 5 4 3 4
Construct a network and find critical path, total duration of the
project and calculate EST, LST, EFT and LFT.
07

Q.3 (a) Discuss about resource allocation in project management. 03
(b) Explain project termination in brief. 04
(c) Define project management and explain how it differs from
general management.
07
OR
Q.3 (a) Discuss regarding cost variance in project. 03
(b) Explain in brief about project overview statement. 04
(c) Explain different elements of project planning. 07

Q.4 (a) Define following terms:
(i) Optimistic time, (ii) Pessimistic time, (iii) Most likely time
03
(b) Explain budgeting of project in brief. 04
(c) Discuss work breakdown structure with suitable example. 07
OR
Q.4 (a) Explain about project cost estimation. 03
(b) Explain how project evaluation is useful in project management. 04
(c) Explain the process of project auditing. 07

Q.5 (a) Discuss about project action plan. 03
(b) Explain project scope creep in brief. 04
FirstRanker.com - FirstRanker's Choice
1
Seat No.: ________ Enrolment No.___________

GUJARAT TECHNOLOGICAL UNIVERSITY

BE - SEMESTER ? VIII (New) EXAMINATION ? WINTER 2019
Subject Code: 2182506 Date: 25/11/2019

Subject Name: Managing Projects
Time: 02:30 PM TO 05:00 PM Total Marks: 70

Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.


MARKS

Q.1 (a) Explain scope, schedule and cost in reference to project
management.
03
(b) Explain guidelines for construction of network diagram.

04
(c) Differentiate two methods: CPM and PERT with its application 07

Q.2 (a) Draw the AOA network for the following project:
Activity A B C D E F G H
Predecessor - - A B A C,D C,D,E F

03
(b) Explain budget uncertainty in project management. 04
(c) Explain project manager?s role and responsibility in project. 07
OR
(c) A project schedule has the following characteristics
Activity A B C D E F
Predecessor - A B A D C,E
Duration(week) 5 6 5 4 3 4
Construct a network and find critical path, total duration of the
project and calculate EST, LST, EFT and LFT.
07

Q.3 (a) Discuss about resource allocation in project management. 03
(b) Explain project termination in brief. 04
(c) Define project management and explain how it differs from
general management.
07
OR
Q.3 (a) Discuss regarding cost variance in project. 03
(b) Explain in brief about project overview statement. 04
(c) Explain different elements of project planning. 07

Q.4 (a) Define following terms:
(i) Optimistic time, (ii) Pessimistic time, (iii) Most likely time
03
(b) Explain budgeting of project in brief. 04
(c) Discuss work breakdown structure with suitable example. 07
OR
Q.4 (a) Explain about project cost estimation. 03
(b) Explain how project evaluation is useful in project management. 04
(c) Explain the process of project auditing. 07

Q.5 (a) Discuss about project action plan. 03
(b) Explain project scope creep in brief. 04
2
(c) What is resource loading? How does it differ from resource
leveling?
07
OR

Q.5 (a) Explain about crashing of cost in brief. 03
(b) Explain how the project team reflects on successful completion
of project.
04
(c) Explain project management life cycle with neat sketch. 07

*************

FirstRanker.com - FirstRanker's Choice