Download GTU (Gujarat Technological University) BE/BTech (Bachelor of Engineering / Bachelor of Technology) 2017 Winter 3rd Sem Old 133405 Manufacturing And Assembly Drawing Previous Question Paper
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER ?III (OLD) EXAMINATION ? WINTER 2017
Subject Code:133405 Date:29/11/2017
Subject Name: Manufacturing and Assembly Drawing
Time: 10:30 AM to 01:00 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q.1 (a) Define Tolerance, Unilateral Tolerance, and Bilateral Tolerance with
suitable sketches.
07
(b) What is a production drawing? Why production drawings must be
prepared as per standard.
07
Q.2 (a) Name the different types of Rivet Heads. What is the function of a cover
plate in riveted joints?
07
(b) Differentiate between lap joint and butt joint, Chain riveting and zigzag
riveting.
07
OR
(b) Explain about Hole basis system with the help of a suitable example. 07
Q.3 (a) Draw the conventions for following machine elements:
i) Ratchet and pinion. ii) Holes on a linear pitch.
iii) Helical Torsion Spring. iv) Disc spring stacked in parallel.
07
(b) Draw to 1:1 scale, the top view and sectional front view of a single riveted butt
joint with double cover plates. The thickness of plates is 9 mm. Show at least
three rivets in each row. Indicate all dimensions. Use snap head rivets.
07
OR
Q.3 (a) Define the following:
i) Basic Size, ii) Actual Size, iii) Tolerance, iv) Deviation.
07
(b) Define fit. Classify fits. Briefly explain about them. 07
Q.4 Fig.1 shows the detail drawing of the different parts of a Cotter Joint with
Sleeve. Assemble all the parts and draw the front view in Section.
14
FirstRanker.com - FirstRanker's Choice
1
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER ?III (OLD) EXAMINATION ? WINTER 2017
Subject Code:133405 Date:29/11/2017
Subject Name: Manufacturing and Assembly Drawing
Time: 10:30 AM to 01:00 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q.1 (a) Define Tolerance, Unilateral Tolerance, and Bilateral Tolerance with
suitable sketches.
07
(b) What is a production drawing? Why production drawings must be
prepared as per standard.
07
Q.2 (a) Name the different types of Rivet Heads. What is the function of a cover
plate in riveted joints?
07
(b) Differentiate between lap joint and butt joint, Chain riveting and zigzag
riveting.
07
OR
(b) Explain about Hole basis system with the help of a suitable example. 07
Q.3 (a) Draw the conventions for following machine elements:
i) Ratchet and pinion. ii) Holes on a linear pitch.
iii) Helical Torsion Spring. iv) Disc spring stacked in parallel.
07
(b) Draw to 1:1 scale, the top view and sectional front view of a single riveted butt
joint with double cover plates. The thickness of plates is 9 mm. Show at least
three rivets in each row. Indicate all dimensions. Use snap head rivets.
07
OR
Q.3 (a) Define the following:
i) Basic Size, ii) Actual Size, iii) Tolerance, iv) Deviation.
07
(b) Define fit. Classify fits. Briefly explain about them. 07
Q.4 Fig.1 shows the detail drawing of the different parts of a Cotter Joint with
Sleeve. Assemble all the parts and draw the front view in Section.
14
2
OR
Q.4 Details of a flanged coupling (Unprotected type) are shown in Fig. 2. Draw to
1:1 scale the front view with top half in section, showing all the parts
assembled, with one of the shaft being projected by a distance of 5 mm into
the bore of the other flange.
14
Q.5 Fig. 3 shows the assembly drawing of a petrol engine connecting rod. Prepare
working drawings of CAP & Bearing Brass.
14
OR
Q.5 Draw the assembly drawing of a two plate injection mould (Two cavity) for a
cup (PP material) of outside diameter 40 mm, total height of 20 mm and wall
thickness 1.5 mm. Mention the BOM.
14
FirstRanker.com - FirstRanker's Choice
1
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER ?III (OLD) EXAMINATION ? WINTER 2017
Subject Code:133405 Date:29/11/2017
Subject Name: Manufacturing and Assembly Drawing
Time: 10:30 AM to 01:00 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q.1 (a) Define Tolerance, Unilateral Tolerance, and Bilateral Tolerance with
suitable sketches.
07
(b) What is a production drawing? Why production drawings must be
prepared as per standard.
07
Q.2 (a) Name the different types of Rivet Heads. What is the function of a cover
plate in riveted joints?
07
(b) Differentiate between lap joint and butt joint, Chain riveting and zigzag
riveting.
07
OR
(b) Explain about Hole basis system with the help of a suitable example. 07
Q.3 (a) Draw the conventions for following machine elements:
i) Ratchet and pinion. ii) Holes on a linear pitch.
iii) Helical Torsion Spring. iv) Disc spring stacked in parallel.
07
(b) Draw to 1:1 scale, the top view and sectional front view of a single riveted butt
joint with double cover plates. The thickness of plates is 9 mm. Show at least
three rivets in each row. Indicate all dimensions. Use snap head rivets.
07
OR
Q.3 (a) Define the following:
i) Basic Size, ii) Actual Size, iii) Tolerance, iv) Deviation.
07
(b) Define fit. Classify fits. Briefly explain about them. 07
Q.4 Fig.1 shows the detail drawing of the different parts of a Cotter Joint with
Sleeve. Assemble all the parts and draw the front view in Section.
14
2
OR
Q.4 Details of a flanged coupling (Unprotected type) are shown in Fig. 2. Draw to
1:1 scale the front view with top half in section, showing all the parts
assembled, with one of the shaft being projected by a distance of 5 mm into
the bore of the other flange.
14
Q.5 Fig. 3 shows the assembly drawing of a petrol engine connecting rod. Prepare
working drawings of CAP & Bearing Brass.
14
OR
Q.5 Draw the assembly drawing of a two plate injection mould (Two cavity) for a
cup (PP material) of outside diameter 40 mm, total height of 20 mm and wall
thickness 1.5 mm. Mention the BOM.
14
3
FirstRanker.com - FirstRanker's Choice
1
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER ?III (OLD) EXAMINATION ? WINTER 2017
Subject Code:133405 Date:29/11/2017
Subject Name: Manufacturing and Assembly Drawing
Time: 10:30 AM to 01:00 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q.1 (a) Define Tolerance, Unilateral Tolerance, and Bilateral Tolerance with
suitable sketches.
07
(b) What is a production drawing? Why production drawings must be
prepared as per standard.
07
Q.2 (a) Name the different types of Rivet Heads. What is the function of a cover
plate in riveted joints?
07
(b) Differentiate between lap joint and butt joint, Chain riveting and zigzag
riveting.
07
OR
(b) Explain about Hole basis system with the help of a suitable example. 07
Q.3 (a) Draw the conventions for following machine elements:
i) Ratchet and pinion. ii) Holes on a linear pitch.
iii) Helical Torsion Spring. iv) Disc spring stacked in parallel.
07
(b) Draw to 1:1 scale, the top view and sectional front view of a single riveted butt
joint with double cover plates. The thickness of plates is 9 mm. Show at least
three rivets in each row. Indicate all dimensions. Use snap head rivets.
07
OR
Q.3 (a) Define the following:
i) Basic Size, ii) Actual Size, iii) Tolerance, iv) Deviation.
07
(b) Define fit. Classify fits. Briefly explain about them. 07
Q.4 Fig.1 shows the detail drawing of the different parts of a Cotter Joint with
Sleeve. Assemble all the parts and draw the front view in Section.
14
2
OR
Q.4 Details of a flanged coupling (Unprotected type) are shown in Fig. 2. Draw to
1:1 scale the front view with top half in section, showing all the parts
assembled, with one of the shaft being projected by a distance of 5 mm into
the bore of the other flange.
14
Q.5 Fig. 3 shows the assembly drawing of a petrol engine connecting rod. Prepare
working drawings of CAP & Bearing Brass.
14
OR
Q.5 Draw the assembly drawing of a two plate injection mould (Two cavity) for a
cup (PP material) of outside diameter 40 mm, total height of 20 mm and wall
thickness 1.5 mm. Mention the BOM.
14