Download PTU (I.K. Gujral Punjab Technical University Jalandhar (IKGPTU) ) BE/BTech CSE/IT (Computer Science And Engineering/ Information Technology) 2020 March 7th and 8th Sem BTCS 907 Software Project Management Previous Question Paper
Roll No. Total No. of Pages : 02
Total No. of Questions : 18
B.Tech.(CSE) (2012 to 2017 E-II) (Sem.?7,8)
SOFTWARE PROJECT MANAGEMENT
Subject Code : BTCS-907
M.Code : 71899
Time : 3 Hrs. Max. Marks : 60
INSTRUCTION TO CANDIDATES :
1. SECTION-A is COMPULSORY consisting of TEN questions carrying TWO marks
each.
2. SECTION-B contains FIVE questions carrying FIVE marks each and students
have to attempt any FOUR questions.
3. SECTION-C contains THREE questions carrying TEN marks each and students
have to attempt any TWO questions.
SECTION-A
Write briefly :
1) Write any one software process model.
2) Define COCOMO2 model.
3) What is meant by cost flow forecasting?
4) Define monte carlo simulation.
5) What is Project Sequencing?
6) What is software Quality Assurance Plan?
7) Discuss significance of Network planning.
8) Discuss Hackman & Oldham?s Job Characteristics Model.
9) What are the benefits of test automation?
10) Write a short note on Software Reliability.
FirstRanker.com - FirstRanker's Choice
1 | M - 7 1 8 9 9 ( S 2 ) - 1 1 8 7
Roll No. Total No. of Pages : 02
Total No. of Questions : 18
B.Tech.(CSE) (2012 to 2017 E-II) (Sem.?7,8)
SOFTWARE PROJECT MANAGEMENT
Subject Code : BTCS-907
M.Code : 71899
Time : 3 Hrs. Max. Marks : 60
INSTRUCTION TO CANDIDATES :
1. SECTION-A is COMPULSORY consisting of TEN questions carrying TWO marks
each.
2. SECTION-B contains FIVE questions carrying FIVE marks each and students
have to attempt any FOUR questions.
3. SECTION-C contains THREE questions carrying TEN marks each and students
have to attempt any TWO questions.
SECTION-A
Write briefly :
1) Write any one software process model.
2) Define COCOMO2 model.
3) What is meant by cost flow forecasting?
4) Define monte carlo simulation.
5) What is Project Sequencing?
6) What is software Quality Assurance Plan?
7) Discuss significance of Network planning.
8) Discuss Hackman & Oldham?s Job Characteristics Model.
9) What are the benefits of test automation?
10) Write a short note on Software Reliability.
2 | M - 7 1 8 9 9 ( S 2 ) - 1 1 8 7
SECTION-B
11) What are the steps in cost-benefit analysis? Discuss the cost-benefit evaluation
techniques.
12) Define following :
a. Types of Risk Management
b. Schedule compression
13) Illustrate the PERT method for identifying the critical path of project.
14) Distinguish between CMMI and ISO models.
15) What are the criteria for selecting the right person for the Job?
SECTION-C
16) Write in detail the monitoring and control of software project management cycle.
17) Discuss common aspects of Contract Management. What are the types of Contracts and
its stages?
18) Explain different approaches for Project Management. Give the overview of any one tool
for Project Management.
NOTE : Disclosure of Identity by writing Mobile No. or Making of passing request on any
page of Answer Sheet will lead to UMC against the Student.
FirstRanker.com - FirstRanker's Choice
This post was last modified on 21 March 2020