Code No: 723AA
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
MBA III Semester Examinations, June/July-2018
PRODUCTION AND OPERATIONS MANAGEMENT
Time: 3hours Max.Marks:75

Note: This question paper contains two parts A and B.
Part A is compulsory which carries 25 marks. Answer all questions in Part A.
Part B consists of 5 Units. Answer any one full question from each unit. Each question
carries 10 marks and may have a, b, c as sub questions.

PART - A 5 ? 5 Marks = 25

1.a) What is ?Process Characteristics Matrix?? [5]
b) Discuss the various causes that require value analysis. [5]
c) What are the Limitations of Product Layout? [5]
d) Explain briefly about Palmer?s Heuristic procedure. [5]
e) Write a short note on VED Analysis. [5]

PART - B 5 ? 10 Marks = 50

2. What are the characteristics of a service system? Explain different types of Production
systems and mention suitable examples. [10]
OR
3. Define ?Productivity?. Explain different strategies for improving overall productivity in an
organization. [10]

4. Explain different ergonomic considerations while designing products. [10]
OR
5. Alpha Industry is planning for expanding its production operation. It has identified three
different technologies for meeting the goal. The initial outlay and annual revenues with
respect to each of the technologies are summarized in the following table. Suggest the best
technology which has to be implemented based on present worth method of comparison
assuming 20% interest rate compounded annually. [10]

Initial
Outlay
(Rs.)
Annual
Revenue
(Rs)
Life
(Years)
Technology 1 12,00,000 4,00,000 15
Technology 2 20,00,000 6,00,000 15
Technology 3 18,00,000 5,00,000 15

R15
www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
FirstRanker.com - FirstRanker's Choice
www.FirstRanker.com


Code No: 723AA
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
MBA III Semester Examinations, June/July-2018
PRODUCTION AND OPERATIONS MANAGEMENT
Time: 3hours Max.Marks:75

Note: This question paper contains two parts A and B.
Part A is compulsory which carries 25 marks. Answer all questions in Part A.
Part B consists of 5 Units. Answer any one full question from each unit. Each question
carries 10 marks and may have a, b, c as sub questions.

PART - A 5 ? 5 Marks = 25

1.a) What is ?Process Characteristics Matrix?? [5]
b) Discuss the various causes that require value analysis. [5]
c) What are the Limitations of Product Layout? [5]
d) Explain briefly about Palmer?s Heuristic procedure. [5]
e) Write a short note on VED Analysis. [5]

PART - B 5 ? 10 Marks = 50

2. What are the characteristics of a service system? Explain different types of Production
systems and mention suitable examples. [10]
OR
3. Define ?Productivity?. Explain different strategies for improving overall productivity in an
organization. [10]

4. Explain different ergonomic considerations while designing products. [10]
OR
5. Alpha Industry is planning for expanding its production operation. It has identified three
different technologies for meeting the goal. The initial outlay and annual revenues with
respect to each of the technologies are summarized in the following table. Suggest the best
technology which has to be implemented based on present worth method of comparison
assuming 20% interest rate compounded annually. [10]

Initial
Outlay
(Rs.)
Annual
Revenue
(Rs)
Life
(Years)
Technology 1 12,00,000 4,00,000 15
Technology 2 20,00,000 6,00,000 15
Technology 3 18,00,000 5,00,000 15

R15
www.FirstRanker.com www.FirstRanker.com
www.FirstRanker.com
www.FirstRanker.com


6. The coordinates of the three existing facilities are (4,3) (6,8) and (9,5). Two new facilities
are added along with the three existing facilities and flow between the new facilities is 10
tones of materials/ day. The flows of material from the new facilities to the different existing
facilities are shown as below:

New
Facility
Existing Facility
1 2 3
1 10 12 19
2 8 13 11
Formulate a linear programming model to find the coordinates of the new facilities such that
the total material handling cost is minimized. Solve the model. [10]
OR
7. How do you classify Layouts? Illustrate. Discuss in detail the advantages and limitations of
group technology Layout. [10]

8. Consider the following three machines and 5 jobs flow shop problem. Apply Johnson?s
Rule. [10]
Processing Time
Job Machine 1 Machine 2 Machine 3
1 8 5 4
2 10 6 9
3 6 2 8
4 7 3 6
5 11 4 5
OR
9. What is Job shop scheduling Problem? Discuss different types of schedules in detail. [10]

10. What is Analytic Hierarchy Process (AHP)? Explain the steps of Analytic Hierarchy Process
(AHP). [10]
OR
11.a) Distinguish between P and Q systems of Inventory.
b) Ram Industry needs 5400units/year of a bought out component which will be in its
main product. The ordering cost is Rs.250 per order and the carrying cost per unit per
year is Rs.30. Find out Economic Order Quantity, Number of orders per year, Time
between successive orders. [5+5]

--ooOoo--