Download PTU B.Tech 2021 Jan EE 5th Sem 70555 Electric Generation And Economics Question Paper

Download PTU (Punjab Technical University) B.Tech (Bachelor of Technology) / BE (Bachelor of Engineering) 2021 January EE 5th Sem 70555 Electric Generation And Economics Previous Question Paper


Roll No.
Total No. of Pages : 03
Total No. of Questions : 18
B.Tech. (EE) PT (Sem.?5)
ELECTRIC GENERATION & ECONOMICS
Subject Code : BTEE-502
M.Code : 70555
Time : 3 Hrs. Max. Marks : 60
INST RUCT ION TO CANDIDAT ES :
1 .
SECT ION-A is COMPULSORY cons is ting of TEN questions carrying TWO marks
each.
2 .
SECT ION-B c ontains F IVE questions c arrying FIVE marks eac h and s tud ents
have to atte mpt any FOUR q ues tions.
3 .
SECT ION-C contains THREE questions carrying T EN marks e ach and s tudents
have to atte mpt any T WO questio ns.
SECTION-A
Answer briefly :
1.
What are peak load plants?
2.
What do you mean by a load duration curve?
3.
Define utilization factor.
4.
Discuss the effect of load factor on cost of energy.
5.
Define power factor.
6.
What are the objectives of tariff making?
7.
Discuss the methods of loading turbo generators.
8.
What do you mean by hydrothermal scheduling?
9.
Write a short note on the impact of power plant pollution of aquatic life.
10. Discuss the scope of cogeneration in India.
1 | M-70555
(S2)- 48


SECTION-B
11. The yearly load duration of a power plant is a straight line. The maximum load is 30 MW
and the minimum load is 20 MW. The capacity of the plant is 35 MW. Find (a) plant
capacity factor (b) load factor
12. A region has a maximum demand of 500 MW at a load factor of 50%. The load duration
curve can be assumed to be a triangle. The utility has to meet this load by setting up a
generating system which is partly hydro and partly thermal. The costs are as under:
Hydro plant: Rs 7200 per kW per annum + operating expenses Rs 0.36 per kWh.
Thermal plant Rs. 3600 per kW per annum + operating expenses Rs 1.56 per kWh.
Determine the capacity of hydro plant, capacity of thermal plant, energy generated annually
by each and overall generation cost per kWh.
13. A steam plant having an installed capacity of 200 MW is to be set up. The investment on
the plant is Rs. 12,000 per kW of installed capacity. The useful life of the plant may be
taken as 25 years and salvage value of plant is 25% of initial cost. Find the annual
depreciation reserve by :
a) Straight line method.
b) Sinking fund method if interest rate is 8 %.
14. What considerations govern the selection of sites for steam plants? How does the plant
location affect the reliability of electric supply?
15. The incremental costs in Rs. Per MW-hour of two 250 MW units are as under:
dC1 0 3.P 40
1
dP1
dC2 0 2.P 40
2
dP2
The minimum load of each is 30 MW. Find the load division between the two units as the
total load varies from 40 MW to 500 MW.
2 | M-70555
(S2)- 48


SECTION-C
16. A system consists of two plants (i.e. Plant 1 and Plant 2) connected by a transmission line.
The load is at plant 2. The transmission line loss calculations reveal that a transfer of 100
MW from plant 1 to plant 2 means a loss of 15 MW. Find the required generation at each
plant for - 60. Assume that the incremental costs of the two plants are given as:
dC1 0 2.P 22Rs / MWh
1
dP1
dC2 0 1.5P 30Rs / MWh
2
dP2
17. a) What are the different types of tariffs? Explain them in detail.
b) Discuss the various methods of power factor improvement.
18. Explain briefly :
a) Topping and Bottoming Cycles
b) Hydro-thermal co-ordination
NOTE : Disclosure of Identity by writing Mobile No. or Making of passing request on any
page of Answer Sheet will lead to UMC against the Student.
3 | M-70555
(S2)- 48

This post was last modified on 26 June 2021