Code: 9E00204

MBA & MBA (Finance) II Semester Supplementary Examinations December/January 2015/2016
PRODUCTION & OPERATIONS MANAGEMENT
(For students admitted in 2011, 2012, 2013 & 2014)


Time: 3 hours Max. Marks: 60

Answer any FIVE questions
All questions carry equal marks
*****
1 (a) Define production and operations management and discuss different types of production systems
with suitable examples.
(b) Briefly discuss functions of production and operations management.

2 Illustrate the product design process with a suitable example.

3 There are five existing facilities which are to be served by a single new facility. The details of the
existing facilities are shown in the following table.
Existing facility 1 2 3 4 5
Coordinates (a
i
, b
i
) 5.10 20.5 15.20 30.25 25.5
No. of trips of loads/year 100 300 200 300 100
Find the optimum location of the new facility based on gravity location concept.

4 Briefly explain different long term and short term capacity strategies.

5 (a) What is job scheduling problem? Distinguish it from flow shop scheduling problem with a suitable
example.
(b) Explain the active schedule, semi active schedule and non-delay schedule.

6 (a) Distinguish between method study and time study.
(b) Briefly discuss different steps in work sampling.

7 (a) Discuss various ways of improving productivity.
(b) Discuss the concepts of productivity cycle, productivity engineering and management.

8 The following table gives the number of missing rivets noted in a newly fabricated bus. Construct a
C-chart.
Bus No. 1 2 3 4 5 6 7 8 9 10
No. of missing rivets 14 13 26 20 9 25 15 11 14 13


*****